File #: 09-1286    Version: 1 Name: FY 2009 Water Main Replacement Change Order No.1
Type: committee action item Status: Joint Committee
File created: 2/26/2009 In control: Public Works and Transportation Committee
On agenda: Final action: 3/4/2009
Title: Joint committee action approving Change Order No. 1 for design work on the FY 2009 Water Main Replacement Project.
Attachments: 1. 2009.03.04 Change Order No.1.pdf

Title

Joint committee action approving Change Order No. 1 for design work on the FY 2009 Water Main Replacement Project.

 

Staff Summary

                     Change Order No. 1 for additional consulting engineering work on the FY 2009 Water Main Replacement Project is in the net amount of $14,056.97.

                     This change order includes additional scope of work for design of approximately 850 lineal feet of water main on Lake Shore Drive in the Wildwood Water System.

                     This section of water main has failed recently causing localized flooding to homes and is in need of full replacement.

                     The addition of Change Order No.1 increases the contract amount from $86,558 to $100,614.97 resulting in an overall project increase of 16.2%.

                     Change orders that exceed 10% of the total contract amount must be approved by the PW & T and F & A Committees.