Title
Joint committee action item approving Change Order No. 6 consisting of a decrease of $105,146.24 for deductions to the Skokie Valley Bike Path’s Construction Contract, designated as Section No. 94-00241-00-BT.
Staff Summary
• Skokie Valley Bike Path: LCDOT Change Order No. 6
• Change Orders need to be approved by the standing committees for cumulative net increases over 10%.
• Skokie Valley Bike Path project is under contract with V3 Construction Group, under an awarded contract at bid unit prices totaling $2,155,250.
• Previous change orders 1 thru 5 dealt with extra work at unit prices (net 10 %+).
• At the end of construction, a final listing of quantities of work completed at the unit prices is created.
• This is called a balancing change order as some quantities are less than planned and some are more.
• This balancing Change Order No. 6 is a net decrease of $105,146.24.
• Summary: Original awarded contract - $ 2,155,250; Change Order No. 6 - ($105,146.24); sum of all changes - $ 432,663.94