Title
Joint committee action item approving Change Order No. 1 & final for the Skokie Valley Bike Path from Laurel Ave. to IL Rte. 176, designated as Section No. 94-00241-00-BT.
Staff Summary
• Change orders need to be approved by the standing committees for cumulative net increases over 10%.
• The Skokie Valley Bike Path project is under an original engineering contract proposal totaling $194,309.
• The construction contract on this project exceeded the original completion date due to additional requirements from the land owners (Com Ed & Union Pacific Railroad).
• As a result, the construction inspection consultant required additional time and expense for this added construction time frame. Summary: Original contract - $194,309; Change Order No. 1 - $25,685; sum of all changes - $25,685.