Resolution authorizing an agreement with DLR Group, Chicago, Illinois for professional architectural and engineering services for the Robert W. Depke Juvenile Complex Center in Vernon Hills in the amount of $694,000.
Staff Summary
* During the Facilities Capital Improvement Plan process (in Fiscal Year 2021), the Depke Phase 2 Bridge project was approved.
* Facilities and Construction Services identified the need to continue the remodeling of the old Courthouse entrance lobby, original courtroom/hearing room area, update the FACE-IT Program and justice agency office areas to accommodate adapted office space for justice agencies to operate more efficiently.
* The scope of services include Architectural, Engineering and Consulting services required for completion of the Phase 2 Bridge Projects Robert W. Depke Juvenile Justice Complex, preparation of contract documents, bidding, construction administration, and all other ancillary design services as required.
* This resolution authorizes the execution of an agreement with DLR Group, of Chicago, IL, in an estimated amount of $694,000.
Body
R E S O L U T I O N
WHEREAS, As part of Capital Improvement Plan, the Robert W. Depke Juvenile Justice Complex Phase 2 Bridge projects was approved; and
WHEREAS, The Facility Master Plan will review departmental level staffing needs and space requirements, projected staffing needs, use and organization of spaces, adjacencies and efficiencies with other departments, and will provide recommendations on future capital development with rough order of magnitude cost estimates; and
WHEREAS, Lake County has selected DLR Group, in accordance with the Local Government Professional Services Selection Act, 50 ILCS 510/1 et. seq
NOW, THEREFORE BE IT RESOLVED by this Lake County Board, that the Purchasing Agent is authorized and directed to execute on behalf of Lake County, an agreement, and any amendments, between DLR Group in the estimated amount of $694,000 for Lake Co...