Title
Joint committee action item approving Change Order Number Three consisting of an increase of $53,379 for additions to the Russell Road intersections improvement Phase II engineering services contract.
Staff Summary
• Change Orders need to be approved by the standing committees for cumulative net increases over 10 percent.
• The Russell Road intersections improvement project is under contract with GFT Infrastructure, Inc., Schaumburg, Illinois, in the amount of $1,204,887 as approved by the County Board on March 8, 2022, and designated as Section 18-00999-57-EG.
• The sum of all contract change orders to date is $171,928, which represents a 14.3% increase over the original awarded contract amount.
Body
JOINT COMMITTEE ACTION ITEM
Summary:
Original awarded contract: $1,204,887
Change Order Number Three: $ 53,379
Previously Approved Change Order Number Two: Zero-Sum amount
Previously Approved Change Order Number One: $ 118,549
Sum of all Change Orders: $ 171,928
Total revised contract amount (including all change orders): $1,376,815
Original contract appropriation amount: $1,450,000