File #: 10-0717    Version: 1 Name: Cedar Lake Road Extension Phase II: Change Order No. 2
Type: committee action item Status: Passed
File created: 7/28/2010 In control: Public Works and Transportation Committee
On agenda: Final action: 7/30/2010
Title: Joint committee action item approving Change Order No. 2 consisting of an increase of $11,597.85 for additions to the Phase II engineering services for the Cedar Lake Road Extension from IL Rte 120 to IL Rte 60 and designated as Section 00-00266-00-FP.
Attachments: 1. Cedar Lake Road Extension Phase II: Change Order No. 2

Title

Joint committee action item approving Change Order No. 2 consisting of an increase of $11,597.85 for additions to the Phase II engineering services for the Cedar Lake Road Extension from IL Rte 120 to IL Rte 60 and designated as Section 00-00266-00-FP.

 

Staff Summary

                     Cedar Lake Road Extension Phase II: Change Order No. 2

                     Change Orders need to be approved by the standing committees for cumulative net increases over 10%.

                     The Cedar Lake Road Extension project is under contract with TranSystems Corporation, Schaumburg, IL in the amount of $713,199.10.

                     Additional environmental engineering services are being requested for several revisions to the original scope of work as detailed in the attached supplement No. 2.

                     Summary: Original awarded contract: $598,493.00; Change Order No. 2: $11,597.85; Sum of all changes: $126,303.85.

 