Title
Approval of Contract authorization with Everlast Blacktop, Inc. Elgin, IL for the Round Lake Drain Master Plan Phase 1 Project, Round Lake Beach, IL in the amount of $1,288,849.30.
Staff Summary
• A total of seven bids were received, ranging from $1,288,849.30 to $1,622,040.00, and the lowest responsible bidder is Everlast Blacktop, Inc. Elgin, IL with a contract amount of $1,288,849.30.
• The project is included in the approved resolution accepting the grant award and emergency appropriation for DCEO-STOCIP Regional Stormwater Infrastructure Project Round 2 Projects that was approved September 5, 2024.
• The project is included in the approved Intergovernmental Agreement with the Village of Round Lake Beach for the Round Lake Drain Master Plan Phase 1 Project that was approved November 6, 2024.
• This project has been identified by SMC staff and the Village of Round Lake Beach as an important project that will reduce safety concerns and risks due to flooding and will improve access to residents and businesses in their community.
• SMC staff recommends approval of the Contract authorization with Everlast Blacktop, Inc. Elgin, IL for the Round Lake Drain Master Plan Phase 1 Project, Round Lake Beach, IL in the amount of $1,288,849.30.