File #: 21-1489    Version: 1 Name: Illinois Route 137 Bike Path (Patriot Path): Phase I Consultant Change Order Number Two
Type: committee action item Status: Joint Committee
File created: 9/27/2021 In control: Public Works, Planning & Transportation Committee
On agenda: Final action: 10/7/2021
Title: Joint committee action item approving Change Order Number Two consisting of an increase of $143,098.56 for additions to the Illinois Route 137 Bike Path (Patriot Path) Phase I consultant agreement.
Attachments: 1. 21-1489 IL Route 137 Bike Path CAM CO #2, 2. 21-1489 IL Route 137 Bike Path PH I Supplement 2, 3. 21-1489 Location Map, IL 137 Phase I, 4. 21-1489 Vendor Disclosure, HR Green

Title

Joint committee action item approving Change Order Number Two consisting of an increase of $143,098.56 for additions to the Illinois Route 137 Bike Path (Patriot Path) Phase I consultant agreement.

 

Staff Summary

•                     Change Orders need to be approved by the standing committees for cumulative net increases over 10 percent.

•                     The Illinois Route 137 Bike Path (Patriot Path) project is under contract with HR Green, Inc., McHenry, Illinois, in the amount of $1,360,893.69 as approved by the County Board on May 12, 2015 and designated as Section 15-00289-01-BT. 

•                     The sum of all contract change orders to date is $271,991.58, which represents a 19.99 percent increase over the original awarded contract amount.

 

Body

COMMITTEE ACTION ITEM

 

Summary:

 

Original awarded contract:                     $1,360,893.69

 

Change Order Number One:                     $128,893.02

Change Order Number Two:                     $143,098.56

Sum of all Change Orders:                     $271,991.58

 

Total revised contract amount (including all change orders): $1,632,885.27.

 

Original contract appropriation amount: $1,635,000.