Lake County, IL
File #: 21-1489    Version: 1 Name: Illinois Route 137 Bike Path (Patriot Path): Phase I Consultant Change Order Number Two
Type: committee action item Status: Joint Committee
File created: 9/27/2021 In control: Public Works, Planning & Transportation Committee
On agenda: Final action: 10/7/2021
Title: Joint committee action item approving Change Order Number Two consisting of an increase of $143,098.56 for additions to the Illinois Route 137 Bike Path (Patriot Path) Phase I consultant agreement.
Attachments: 1. 21-1489 IL Route 137 Bike Path CAM CO #2, 2. 21-1489 IL Route 137 Bike Path PH I Supplement 2, 3. 21-1489 Location Map, IL 137 Phase I, 4. 21-1489 Vendor Disclosure, HR Green

Title

Joint committee action item approving Change Order Number Two consisting of an increase of $143,098.56 for additions to the Illinois Route 137 Bike Path (Patriot Path) Phase I consultant agreement.

 

Staff Summary

                     Change Orders need to be approved by the standing committees for cumulative net increases over 10 percent.

                     The Illinois Route 137 Bike Path (Patriot Path) project is under contract with HR Green, Inc., McHenry, Illinois, in the amount of $1,360,893.69 as approved by the County Board on May 12, 2015 and designated as Section 15-00289-01-BT. 

                     The sum of all contract change orders to date is $271,991.58, which represents a 19.99 percent increase over the original awarded contract amount.

 

Body

COMMITTEE ACTION ITEM

 

Summary:

 

Original awarded contract:                     $1,360,893.69

 

Change Order Number One:                     $128,893.02

Change Order Number Two:                     $143,098.56

Sum of all Change Orders:                     $271,991.58

 

Total revised contract amount (including all change orders): $1,632,885.27.

 

Original contract appropriation amount: $1,635,000.