Title
Joint committee action item approving Change Order No. 2 for professional engineering services to improve Wilson Road at Nippersink Road, and designated as Section 03-00070-06-CH.
Staff Summary
· Wilson Road at Nippersink Road Intersection Improvement, Professional Engineering Services: Change Order No. 2.
· Change orders need to be approved by the standing committees for cumulative net increases over 10%.
· Transystems Corporation, Schaumburg, Illinois, was contracted to provide professional engineering services for the design of the intersection improvement in the amount of $374,810.02.
· Additional preliminary engineering services are being requested to evaluate a traffic signal alternative in addition to the completed evaluation of a roundabout, resulting in a net increase over 10% of the original contract, resulting in an adjusted contract cost of $482,017.51.
· Approval of Change Order No. 2 is necessary to complete the project.
Body
Summary:
Original awarded contract: $374,810.02
Change Order No. 1: $ 8,934.00
Change Order No. 2: $ 98,273.49
Sum of all changes: $107,207.49
Adjusted contract cost $482,017.51