Title
Joint committee action item approving Change Order No. 2, consisting of an increase of $45,168.19 for additions to the Peterson Road at IL Route 60 Intersection Improvement’s Engineering Services, designated as Section No. 00-00098-11-CH.
Staff Summary
• Peterson Road at IL Route 60 Intersection Improvement, Engineering Services: LCDOT Change Order No. 2
• Change Orders need to be approved by the standing committees for cumulative net increases over 10%.
• The Peterson Road at IL Route 60 Intersection Improvement project is under contract with Teng and Associates, in the amount of $614,216.30.
• The scope of work covered in this change order is for: update plats to IDOT format for parcels IDOT is now acquiring; provide the detailed structure plans for the extension of the Squaw Creek box culvert; and miscellaneous Phase III coordination and direct costs.
• Summary: original awarded contract - $592,483.12; Change Order No. 2 - $45,168.19; sum of all changes - $659,384.49.