Title
Joint committee action item approving Change Order No. 2, consisting of an increase of $26,935 for additions to the Washington Street Bridge Repair Construction Contract, and designated as Section No. 14-00067-17-BR.
Staff Summary
• Washington Street Bridge Repair: Change Order No. 2.
• Change orders need to be approved by the standing committees for cumulative net increases over 10%.
• The Washington Street bridge repair project is under contract with Sjostrom & Sons, Inc., in the amount of $31,600 for the westbound bridge.
• The major item contributing to this change order is identification, by the contractor, of additional repair work of the nearby bearing assembly at the east abutment of the westbound bridge under the outer lane.
• The design structural engineer and our bridge inspector observed the planned repairs in June, 2014, but there was no issue with the bearing at that time. Since that time, the bearing has rotated and is in need of replacement.
Body
Summary:
Original awarded contract: $31,600
Change Order No. 2: $26,935
Change Order No. 1: $3,110
Sum of all changes and original contract: $61,645