Title
Joint committee action item approving Change Order Number 13 consisting of an increase of $402,374.28 for additions to the Wadsworth Road Improvements Construction Contract, and designated as Section No. 01-00033-10-ES.
Staff Summary
• Wadsworth Road Improvements: Change Order Number 13.
• Change Orders need to be approved by the standing committees for cumulative net increases over 10 percent.
• The Wadsworth Road Improvement Project is under contract with Curran Contracting Company, in the amount of $2,352,557.90.
• The significant items driving this change order are as follows: 1) Paying for additional traffic control; 2) Storm sewer removal, 3) Deeper boring effort under the railroad tracks for a 42” drainage pipe, 4) Adding a middle stage to the construction program to keep one lane open in each direction, and 6) Maintenance of the deteriorating existing road.
Body
Change Order Summary:
Original awarded contract: $2,352,557.90
Change Order Number 13: $175,383.80
Previously approved change orders: $226,990.48
Sum of all changes: $402,374.28