Title
Joint committee action item approving change order number two, consisting of an increase of $144,213.86, for additions to the North Shore Bike Path abutment repairs construction contract, and designated as Section 16-00999-25-BR.
Staff Summary
• North Shore Bike Path Abutment Repairs: LCDOT Change Order Number Two.
• Change orders need to be approved by the standing committees for cumulative net increases over 10 percent.
• North Shore Bike Path abutment repairs project is under contract with Alliance Contractors, Inc. in the amount of $618,683.50.
• The length of this project is approximately 0.057 miles for three century-old railroad bridge abutments holding up the current North Shore Bike Path over the Skokie River, over the Canadian National Railroad, and over the Metra Railroad.
• Change order number two is for additional and deeper concrete repairs required that were not anticipated in the original contract plans.
Body
Summary:
Original awarded contract: $618,683.50
Change Order No. 2: $144,213.86
Change Order No. 1: $59,679.77
Sum of all changes: $203,893.63