Title
Joint resolution authorizing a contract with Path Construction Company, Inc., Arlington Heights, Illinois, in the amount of $72,360 for rehabilitation of the bridge deck on Russell Road over the Des Plaines River, and appropriating $87,000 of County Bridge Tax funds.
Staff Summary
* The bridge deck on Russell Road over the Des Plaines River will be rehabilitated with concrete deck patching and expansion joint replacement.
* There was a public call for bids, and a total of four bids were received, ranging from $72,360 to $140,380, and the lowest responsible bidder is Path Construction Company, Inc., Arlington Heights, Illinois, in the amount of $72,360.
* This project is included in the Transportation Improvement Program with construction to begin in 2026 and designated as Section 25-00078-18-BR.
Body
RESOLUTION
WHEREAS, pursuant to authority granted by this County Board of Lake County, Illinois, the County Engineer heretofore called for sealed bids, by publication, for the rehabilitation of the bridge deck on Russell Road over the Des Plaines River, and designated as Section 25-00078-18-BR; and
WHEREAS, pursuant to said publication calling for said bid, sealed bids were received and opened on October 14, 2025, at 10:00 a.m. at the Lake County Division of Transportation in Libertyville, Illinois; a tabulation of said bids being as follows:
Path Construction Company, Inc.
Arlington Heights, Illinois
$72,360
Lorig Construction Company
Des Plaines, Illinois
$86,628
MYS Incorporated
Palos Heights, Illinois
$108,660.07
Alliance Contractors, Inc.
Woodstock, Illinois
$140,380
WHEREAS, the Public Works and Transportation Committee, the County Engineer and the Purchasing Agent have examined each bid, and it appears that the lowest responsible bidder is Path Construction Company, Inc., Arlington Heights, Illinois, their bid being $72,360, based on estimated quantities and unit prices; and
WHEREAS, an appropriation of funds is required.
NOW, THEREFORE, BE...