Title
Joint resolution authorizing an agreement with Gewalt Hamilton Associates, Inc., Vernon Hills, Illinois, for Phase II design engineering services for the Grass Lake Road Safety Improvement, from State Park Road to Illinois Route 59, at a maximum cost of $219,713, and appropriating $265,000 of Motor Fuel Tax funds.
Staff Summary
* The Grass Lake Road Safety Improvement shall include resurfacing, installation of centerline and shoulder rumble strips, and installation of new pavement markings and markers.
* Lake County selects professional engineering firms in accordance with the Local Government Professional Services Selection Act, 50 ILCS 510/1 et. seq.
* The Lake County Division of Transportation's Consultant Selection Process has been approved by the Federal Highway Administration and the Illinois Department of Transportation, and the firm selected for this project was selected in accordance with this approved process.
* The selected firm has a satisfactory past relationship with the Lake County Division of Transportation.
* This project is included in the Transportation Improvement Program with construction targeted in 2024 and designated as Section 23-00059-14-SP.
Body
RESOLUTION
WHEREAS, Grass Lake Road, County Highway 18, is a designated route on the County highway system; and
WHEREAS, Lake County believes it would be beneficial for the safety and welfare of the traveling public if Grass Lake Road, from State Park Road to Illinois Route 59, could be improved by resurfacing, installation of centerline and shoulder rumble strips, and installation of new pavement markings and markers; and
WHEREAS, it is recommended that a consultant engineering firm be employed to provide Phase II design engineering services for said proposed improvement; and
WHEREAS, Lake County, by and through its Division of Transportation, has selected a professional engineering services firm in accordance with the Local Government Professional Services Selection Act, 50 ILCS...
Click here for full text