Lake County, IL
File #: 13-0338    Version: 1 Name: Joint Resolution authorizing East Main PIG Launch Bolder Construction Contract Award
Type: resolution Status: Passed
File created: 3/15/2013 In control: Public Works and Transportation Committee
On agenda: Final action: 4/9/2013
Title: Joint resolution authorizing the execution of a contract with Bolder Contractors, Inc. in the amount of $256,000 for construction of the East Main Pump Station pipeline inspection gauge launching station.
Attachments: 1. 13-0338 Bid Tab Bolder East Main PIG Launch.pdf
Title
Joint resolution authorizing the execution of a contract with Bolder Contractors, Inc. in the amount of $256,000 for construction of the East Main Pump Station pipeline inspection gauge launching station.

Staff Summary
· As part of the County’s maintenance and rehabilitation of the Northwest Interceptor Sewer it is necessary to clean and test the interceptor as well as perform by-pass pumping of the East Main Pump Station.
· This project will include the construction of a launching station that provides an access point for a pipeline inspection gauge, installation of shut off valves to allow for repairs at the East Main Pump Station, and testing equipment for the interceptor.
· The County received bid documents from seven contractors, five of which were deemed responsive.
· Award of this contract is recommended to the lowest responsive and responsible bidder, Bolder Contractors, Inc., Deerfield, Illinois in the amount of $256,000.00.
· This resolution authorizes execution of a contract with Bolder Contractors, Inc. in the amount of $256,000.

Body
R E S O L U T I O N

WHEREAS, the County of Lake (County) owns, operates and maintains sanitary sewer systems, including the East Main Pump Station and the Northwest Interceptor Sewer (Interceptor) within the Northwest Lake Facility Planning Area; and

WHEREAS, as part of maintenance and rehabilitation of the Northwest Interceptor Sewer it is necessary to clean and test the Interceptor as well as perform by-pass pumping of the East Main Pump Station; and

WHEREAS, in order to perform the maintenance and by-pass pumping, a pipeline inspection gauge (PIG) launching station must be constructed at the East Main Pump Station to allow access to the Interceptor; and

WHEREAS, in accordance with the Lake County Purchasing Ordinance, bids were called for by publication for the construction of a PIG launching station at the East Main Pump Station; and

WHEREAS, subsequent to said ...

Click here for full text