File #: 25-1004    Version: 1 Name: Approval of Contract amendment #1 with ILM, Inc. for Construction Services for Mill Creek Water Quality Enhancement Project in Unincorporated Third Lake, Illinois consisting of an increase of $136,203.94 for a contract amount of $817,223.66
Type: commission action item Status: Passed
File created: 7/23/2025 In control: Lake County Stormwater Management Commission
On agenda: Final action: 8/7/2025
Title: Approval of Contract amendment #1 with Integrated Lakes Management, Inc. for Construction Services for Mill Creek Water Quality Enhancement Project in Unincorporated Third Lake, Illinois consisting of an increase of $136,203.94 for a contract amount of $817,223.66.
Attachments: 1. ILM Mill Creek Contract Amendment #1, 2. Mill Creek Location Map

Title

Approval of Contract amendment #1 with Integrated Lakes Management, Inc. for Construction Services for Mill Creek Water Quality Enhancement Project in Unincorporated Third Lake, Illinois consisting of an increase of $136,203.94 for a contract amount of $817,223.66.

 

Staff Summary

                     Original contract value was an amount of $681,019.72 for the project.

                     This project is being funded by the Lake County Board approved a reallocation of Coronavirus State and Local Fiscal Recovery Funds (CSLFRF) as part of the American Rescue Plan Act (ARPA).

                     This contract change order request is for $136,203.94, which represents a 20.00% increase over the original awarded contract amount.

                     The sum of contract with change orders to date is $817,223.66.

                     Refer to attached change order #1 for a description of all change orders.