Title
Joint committee action item approving Change Order Number Two, consisting of an increase of $12,968.75 for additions to the Hart Road, at U.S. Route 14, Intersection Improvement; Phase II Consultant Agreement, and designated as Section 09-00174-05-CH.
Staff Summary
• Hart Road, at U.S. Route 14, Intersection Improvement, Engineering Services: Change Order No. 2.
• Change orders need to be approved by the standing committees for cumulative net increases over 10 percent.
• The Hart Road, at U.S. Route 14, Intersection Improvement project is under contract with TranSystems, in the amount of $927,604.31.
• Additional engineering services are being requested for several revisions to the original scope including work to revise two parcels on the plat of highways with property needs for the project, based on negotiations between the parcel owners and the Lake County Division of Transportation. This also includes additional environmental work to update the Preliminary Environmental Site Assessment (PESA) and the wetland delineation report that expired in 2015.
Body
Summary:
Original awarded contract: $927,604.31
Change Order No.1: $119,832.67
Change Order No.2: $12,968.75