Approval of the Stormwater Infrastructure Repair Fund (SIRF) Eligibility Authorization for the Bradley Road Industrial Park Property Owners Association’s Stormwater Improvements Project - Phase 1
Staff Summary
• The project involves upsizing a relief sewer to the Bradley Road subdivision detention pond from the surrounding commercial properties and installing an upsized storm sewer at the north end of the detention pond to reduce short-circuiting within the detention pond.
• The proposed project would reduce roadway flooding on a township road, several industrial/commercial properties (including parking lots) and nuisance flooding in the area.
• The estimated project cost for Phase 1 is $394,335.
• Approval of the Eligibility Authorization does not obligate funds. Staff will work with the project applicant to develop a Project Agreement and recommended funding.