Joint committee action item approving Change Order Number One, consisting of an increase of $32,000 for additions to the Buffalo Creek Wetland Bank Phase II Consultant Agreement, and designated as Section No.01-00000-00-ES.
Staff Summary
• Buffalo Creek Wetland Bank, Engineering Services: LCDOT Change Order No. 1.
• Change Orders need to be approved by the standing committees for cumulative net increases over 10 percent.
• The Buffalo Creek Wetland Bank is under contract with Hey & Associates in the amount of $170,500. This $32,000 change order will increase the project cost to $202,500.
• Change Order No. 1 includes work to complete the construction engineering plans and the banking instrument documents in order to receive the permit from the United States Army Corps of Engineers, Lake County Stormwater Management Commission and the Village of Long Grove.
Body
Summary:
Original awarded contract: $170,000
Change Order No.1: $32,000
Sum of all changes: $32,000