Lake County, IL
File #: 09-2123    Version: 1 Name: IL Rte. 120 Corridor Feasibility Study Engineering Services: LCDOT Change Order No. 1
Type: committee action item Status: Joint Committee
File created: 10/26/2009 In control: Public Works and Transportation Committee
On agenda: Final action: 11/4/2009
Title: Joint committee action item approving Change Order No. 1 consisting of an increase of $99,220.06 for additions to the IL Rte. 120 Corridor Feasibility Study’s Engineering Services, designated as Section No. 06-00274-00-ES.
Attachments: 1. 2123 Att_20091028140343.pdf

Title

Joint committee action item approving Change Order No. 1 consisting of an increase of $99,220.06 for additions to the IL Rte. 120 Corridor Feasibility Study’s Engineering Services, designated as Section No. 06-00274-00-ES.

 

Staff Summary

                     IL Rte. 120 Corridor Feasibility Study Engineering Services:  LCDOT Change Order No. 1

                     Change Orders need to be approved by the standing committees for cumulative net increases over 10%.

                     The IL Rte. 120 Corridor Feasibility Study project is under contract with TranSystems, in the amount of $865,439.29.

                     Additional engineering services are being requested for several revisions to the original scope of work as detailed in the attached Supplement No. 1.

                     Summary:  original awarded contract - $865,439.29; Change Order No. 1 - $99,220.06; sum of all changes - $  99,220.06.