File #: 22-1045    Version: 1 Name: Joint Resolution authorizing an agreement with Revere Electric Supply Company, Mokena, Illinois, for the purchase of electrical components for the SCADA Phase 3 project in the amount of $181,643.79.
Type: resolution Status: Passed
File created: 7/21/2022 In control: Public Works, Planning & Transportation Committee
On agenda: Final action: 8/9/2022
Title: Joint Resolution authorizing an agreement with Revere Electric Supply Company, Mokena, Illinois, for the purchase of electrical components for the SCADA Phase 3 project in the amount of $181,643.79.
Attachments: 1. 22-1045 Revere quotes summary, 2. 22-1045 Revere Vendor Disclosure
Title
Joint Resolution authorizing an agreement with Revere Electric Supply Company, Mokena, Illinois, for the purchase of electrical components for the SCADA Phase 3 project in the amount of $181,643.79.

Staff Summary
* The Department of Public Works operates a Supervisory Control and Data Acquisition (SCADA) system, which allows for wireless communication and data collection among the various Public Works water and wastewater systems.
* Public Works is working to implement Phase 3 of the SCADA Master Plan (the SCADA Phase 3 project), which will connect portions of the southeast sewer system to the network, update portions of the central sewer system SCADA network, and update the SCADA network of the former Lakes Region Sanitary District assets.
* Portions of the SCADA Phase 3 project will be implemented by a contractor and portions of the work will be implemented by Public Works electricians, requiring the purchase of electrical components to be installed by the Public Works electricians.
* On December 10, 2020, the Purchasing Division awarded a competitively solicited contract to Revere Electric Supply Company for electrical parts, tech support, as well as purchase discount available for future purchases for the Department of Public Works.
* Public Works received quotes from Revere Electric Supply Company based on the awarded contract.
* This Resolution authorizes the Purchasing Agent to purchase electrical components for the SCADA Phase 3 project from Revere Electric Supply Company, Mokena, Illinois, in the amount of $181,643.79.

Body
RESOLUTION

WHEREAS, the Department of Public Works operates a Supervisory Control and Data Acquisition (SCADA) system, which allows for wireless communication and data collection among the various Public Works water and wastewater systems; and

WHEREAS, Public Works is working to implement Phase 3 of the SCADA Master Plan (SCADA Phase 3 project), which will connect portions of the southeast sewer system to the network, ...