Title
Approval of an Intergovernmental Agreement between the SMC and the Village of Lake Bluff for the West Scranton Avenue Viaduct Project Phase 1 with a Project Expense Match (PEM) value of $311,726.00, subject to final legal review.
Staff Summary
• Funding for the intergovernmental agreement is included in Grant Agreement No. 24-413046 between Lake County and the Illinois Department of Commerce and Economic Opportunity (DCEO) that was executed December 15, 2024.
• This project was authorized by SMC for inclusion in DCEO-STOCIP Regional Stormwater Infrastructure Project Round 2 on September 5, 2024.
• The intergovernmental agreement will provide funding, on a reimbursement basis, to the Village of Lake Bluff in an amount not-to-exceed $2,750,000.00 for the West Scranton Avenue Viaduct Project Phase 1.
• The Village of Lake Bluff will pay a Project Expense Match to SMC of $311,726.00 for administrative and engineering expenses related to the projects.