File #: 10-0602    Version: 1 Name: 2010 Concrete Pavement Patching: Contract Award
Type: resolution Status: Passed
File created: 6/28/2010 In control: Public Works and Transportation Committee
On agenda: Final action: 7/13/2010
Title: Joint resolution authorizing a contract for the concrete pavement patching on various county highways to the lowest responsible bidder, Acura, Inc., Bensenville, Illinois in the amount of $53,837 and provides a supplemental appropriation of $15,000 of Motor Fuel Tax funds for this concrete pavement patching designated as Section 10-00000-14-GM.
Attachments: 1. 2010 Concrete Pavement Patching; Contract Award, 2. justfication letter: 2010 Concrete Pavement Patching; Contract Award
Title
Joint resolution authorizing a contract for the concrete pavement patching on various county highways to the lowest responsible bidder, Acura, Inc., Bensenville, Illinois in the amount of $53,837 and provides a supplemental appropriation of $15,000 of Motor Fuel Tax funds for this concrete pavement patching designated as Section 10-00000-14-GM.
Staff Summary
· 2010 Concrete Pavement Patching; Contract Award
· Each year the Division of Transportation contracts for patching concrete pavements throughout the county highway system.
· A total of 6-bids were received and the lowest responsible bidder is Acura, Inc., Bensenville, Illinois in the amount of $53,837.
· A supplemental appropriation of $15,000 of Motor Fuel Tax funds is provided.

Body
R E S O L U T I O N

WHEREAS, pursuant to authority granted by this Board of Lake County, the County Engineer heretofore called for sealed bids by publication for the concrete pavement patching on various county highways and designated as Section 10-00000-14-GM; and

WHEREAS, pursuant to said publication calling for said bids, sealed bids were received and opened on July 30, 2010, at 10:00 a.m., at the Lake County Division of Transportation in Libertyville, Illinois, a tabulation of said bids being as follows:

Acura Inc.
Bensenville, IL
$58,837.00

Schroeder and Schroeder, Inc.
Skokie, IL
$75,575.00

Alliance Contractors, Inc.,
Woodstock, IL
$104,041.38

Landmark Contractors, Inc.
Huntley, IL
$136,001.25

Triggi Construction, Inc.
West Chicago, IL
$157,317.50

Vixen Construction, Inc.
Bridgeview, IL
$218,104.15

WHEREAS, the Public Works and Transportation Committee, the County Engineer, and the Purchasing Agent have examined each bid, and it appears that the lowest responsible bidder is Acura, Inc., Bensenville, Illinois their bid being $53,837.00 based on estimated quantities and unit prices; and

WHEREAS, this County Board of Lake County, Illinois, by prior re...