Title
Joint resolution authorizing the execution of an agreement between Lake County and V3 Companies of Illinois, Woodridge, Illinois, for Phase III construction engineering services for the widening and reconstruction of Quentin Road at Rand Road at a maximum cost of $869,266.20 and designated as Section 02-00051-08-WR.
Staff Summary
· Quentin Road at Rand Road Widening and Reconstruction; Phase III: Consultant Agreement.
· This improvement will provide increased traffic capabilities by roadway widening to five-lanes.
· A consultant will be utilized to undertake Phase III construction engineering services.
· The selected and recommended firm is V3 Companies of Illinois, Woodridge, Illinois, with a maximum cost of $869,266.20.
Body
R E S O L U T I O N
WHEREAS, Quentin Road, County Highway 5, is a designated route on the county highway system; and
WHEREAS, the free flow of traffic at the intersection of Quentin Road and Rand Road is beneficial to the safety and welfare of the State of Illinois and the county as a whole; and
WHEREAS, the State of Illinois and Lake County believe it would be beneficial to the safety and welfare of the motoring public if the intersection of Quentin Road and Rand Road and Quentin Road from Rue Royal to White Pine Road could be improved by widening and reconstruction; and
WHEREAS, Phase III construction engineering services are required for the Quentin Road widening; and
WHEREAS, it is advisable that a consultant engineering firm be employed to provide said Phase III construction engineering services; and
WHEREAS, Lake County, by and through its Division of Transportation, has selected a professional engineering services firm in accordance with the Local Government Professional Services Selection Act, 50 ILCS 510/1 et. seq.; and
WHEREAS, V3 Companies of Illinois, Woodridge, Illinois, are consulting engineers skilled in the provision of said Phase III construction engineering services.
NOW, THEREFORE BE IT RESOL...