File #: 18-0625    Version: 1 Name: Joint committee action approving Change Order #1 for the Public Works Painting Projects with BP&T Co., Mt. Prospect, IL in the amount of $6,175.
Type: committee action item Status: Passed
File created: 5/30/2018 In control: Public Works and Transportation Committee
On agenda: Final action: 6/6/2018
Title: Joint committee action approving Change Order Number One for Public Works Painting Projects with BP&T Company, Mount Prospect, Illinois, in the amount of $6,175.

Title

Joint committee action approving Change Order Number One for Public Works Painting Projects with BP&T Company, Mount Prospect, Illinois, in the amount of $6,175.

 

Staff Summary

•                     A contract was awarded to BP&T Company for painting lift stations as part of Public Works Painting Projects in November 2017. 

•                     Change Order Number One addresses additional painting work needed at two lift stations that was unforeseen at the time when the project bids were prepared.

•                     In accordance with Article 8, section 101(2) of the Lake County Purchasing Ordinance, this change order was not reasonably foreseeable at the time the contract was signed.

•                     Change Order Number One is in the amount of $6,175, increasing the original contract amount from $25,800 to $31,975.

 

Body

Change Order Request

 

Original awarded contract:                                          $25,800

 

Change Order One:                                                               $ 6,175

 

Sum of all changes:                                          $31,975