Lake County, IL
File #: 10-0017    Version: 1 Name: Skokie Valley Bike Path: LCDOT Change Order No. 6A & Final
Type: committee action item Status: Joint Committee
File created: 12/28/2009 In control: Public Works and Transportation Committee
On agenda: Final action: 1/6/2010
Title: Joint committee action item approving Change Order No. 6A & Final which corrects calculation errors on previous Change Order No. 6, consisting of an increase of $13,068.85 for additions to the Skokie Valley Bike Path’s construction contract, designated as Section No. 94-00241-00-BT.
Attachments: 1. 10 0017_20091228144840.pdf

Title

Joint committee action item approving Change Order No. 6A & Final which corrects calculation errors on previous Change Order No. 6, consisting of an increase of $13,068.85 for additions to the Skokie Valley Bike Path’s construction contract, designated as Section No. 94-00241-00-BT.

 

Staff Summary

                     Skokie Valley Bike Path:  LCDOT Change Order No. 6A & Final

                     Change Orders need to be approved by the standing committees for cumulative net increases over 10%.

                     The Skokie Valley Bike Path project is under a unit price contract with V3 Construction Group, in the total amount of $2,155,250.

                     The design plans for this project were done in the metric system, mandated by IDOT/Feds at the time.

                     Balancing of final construction pay items was presented on Change Order No. 6.  It has since been found, by the consultant Resident Engineer, that some eligible work was inadvertently omitted and calculation errors were discovered involving improper metric system to English system conversion on Change Order No. 6.

                     Original awarded contract: $2,155,250; Change Order No. 6A: $13,038.85; sum of all changes: $445,702.79.