Title
Joint committee action item approving Change Order No. 1 consisting of an increase of $14,770 to the 2010 concrete pavement patching maintenance contract on various county highways and designated as Section 10-00000-14-GM.
Staff Summary
• 2010 Concrete Pavement Patching: Change Order No. 1
• Change Orders need to be approved by the standing committees for cumulative net increases over 10%.
• The awarded construction contract is with Acura, Inc., Bensenville, Illinois in the amount of $53,837.
• Additional traffic control and mobilization services need to be added to the original scope of work as detailed in the attached Request No. 1.
• Summary: Original awarded contract: $53,837; Change Order No. 1: $14,770; Sum of all changes: $14,770.