Title: Joint committee action item approving Change Order No. 2, for additions to the Winchester Road Compensatory Floodplain Storage construction contract, which is an increase of $9,361.35, and designated as Section No. 10-00151-22-CH.
Attachments: 1. 14-1281 Winchester Road Compensatory Floodplain Storage Change Order No 2 Final
Title
Joint committee action item approving Change Order No. 2, for additions to the Winchester Road Compensatory Floodplain Storage construction contract, which is an increase of $9,361.35, and designated as Section No. 10-00151-22-CH.
 
Staff Summary
·      Winchester Road Compensatory Floodplain Storage:  LCDOT Change Order No. 2.
·      Change Orders need to be approved by the standing committees for cumulative net increases over 10 percent.
·      Winchester Road Compensatory Floodplain Storage project is under contract with Berger Excavating Contractors, Inc., in the amount of $90,371.20.
·      After reconciliation of the construction items for the completion of the project, Change Order No. 2 is required.
·      The major item contributing to the cost is adjustment of earth excavation quantity to the actual dimensions performed in the field according to the plans.
 
Body
Summary:
      Original awarded contract:                  $90,371.20
      Change Order No. 2:                  $9,361.35
      Previously approved Change Order 1:                  $779.93
      Sum of all changes:                  $10,141.28