Title
Joint committee action item approving Change Order No. 2, for additions to the Winchester Road Compensatory Floodplain Storage construction contract, which is an increase of $9,361.35, and designated as Section No. 10-00151-22-CH.
Staff Summary
· Winchester Road Compensatory Floodplain Storage: LCDOT Change Order No. 2.
· Change Orders need to be approved by the standing committees for cumulative net increases over 10 percent.
· Winchester Road Compensatory Floodplain Storage project is under contract with Berger Excavating Contractors, Inc., in the amount of $90,371.20.
· After reconciliation of the construction items for the completion of the project, Change Order No. 2 is required.
· The major item contributing to the cost is adjustment of earth excavation quantity to the actual dimensions performed in the field according to the plans.
Body
Summary:
Original awarded contract: $90,371.20
Change Order No. 2: $9,361.35
Previously approved Change Order 1: $779.93
Sum of all changes: $10,141.28