Skip to main content
Lake County, IL
File #: 08-0620    Version: 1 Name: Cedar Lake Road at Monaville Road, Intersection Improvements; Phase I: Consultant Agreement
Type: resolution Status: Passed
File created: 8/28/2008 In control: Public Works and Transportation Committee
On agenda: Final action: 9/9/2008
Title: Joint resolution authorizing the Chair of the County Board, the County Clerk and the County Engineer to execute an agreement between Lake County and Crawford, Murphy and Tilly, Inc., Aurora, Illinois, for the provision of Phase I engineering services (Preliminary Engineering) for the proposed improvements to Cedar Lake Road (County Highway 28) at Monaville Road (County Highway 55) at a maximum cost of services described of $201,034.01. This resolution appropriates $240,000 of Matching Tax funds for these engineering services.
Title
Joint resolution authorizing the Chair of the County Board, the County Clerk and the County Engineer to execute an agreement between Lake County and Crawford, Murphy and Tilly, Inc., Aurora, Illinois, for the provision of Phase I engineering services (Preliminary Engineering) for the proposed improvements to Cedar Lake Road (County Highway 28) at Monaville Road (County Highway 55) at a maximum cost of services described of $201,034.01. This resolution appropriates $240,000 of Matching Tax funds for these engineering services.

Staff Summary
· Cedar Lake Road at Monaville Road, Intersection Improvements; Phase I: Consultant Agreement.
· A consultant will be utilized to undertake Phase I engineering services (Preliminary Engineering) and IDOT approval is required.
· The selected and recommended firm is Crawford, Murphy and Tilly, Inc., Aurora, Illinois.
· This resolution appropriates $240,000 of Matching Tax funds.

Body
R E S O L U T I O N

WHEREAS, Cedar Lake Road (County Highway 28) and Monaville Road (County Highway 55) are designated routes on the county highway system; and

WHEREAS, it would be beneficial for the safety and welfare of the motoring public if the intersection of Cedar Lake Road at Monaville Road could be improved by widening and resurfacing and the installation of permanent traffic control signals or roundabout; and

WHEREAS, Phase I (Preliminary Engineering) studies are required for the proposed improvement to the intersection of Cedar Lake Road at Monaville; and

WHEREAS, it is advisable that a consultant engineering firm be employed to provide said Phase I engineering services (Preliminary Engineering); and

WHEREAS, Lake County by and through its Division of Transportation has selected a professional engineering services firm in accordance with the Local Government Professional Services Selection Act (50 ILCS 510/1 et. seq.); and

WHEREAS, Crawford, Murphy and Tilly, Inc., Aurora, Illinois, are consulting engineers skille...

Click here for full text