Title
Joint Committee action memo approving Change Order No. 4 in the amount of $174,564.83 for revisions to FEMA Flood Plain mapping, the design of soils remediation, the preparation of traffic signal plans at Delany Road intersection with Continental Drive, and revisions and additions to the Plat of Highways prepared for the acquisition of necessary right-of-way.
Staff Summary
· Delany Road Widening (Sunset Avenue to Wadsworth Road), Add Lanes; Phase II Engineering: Change Order No. 4
· Change orders need to be approved by standing committees for cumulative net increases over 10%.
· The change is for revisions to FEMA Flood Plain mapping, the design of soils remediation, the preparation of traffic signal plans at Delaney Road intersection with Continental Drive, and revisions and additions to the Plat of Highways prepared for the acquisition of necessary right-of-way.
Body
Delany Road Widening (Sunset Avenue to Wadsworth Road), Add Lanes; Phase II Engineering: Change Order No. 4
TO: Public Works and Transportation Committee Financial & Administrative Committee DATE: September 3, 2008
FROM:________________________________ Martin G. Buehler County Engineer SUBJECT: LCDOT Consultant Change Order No. 4 Section No.: 00-00093-15-WR
Joint Committee action memo approving Change Order No. 4 in the amount of $174,564.83 for revisions to FEMA Flood Plain mapping, the design of soils remediation, the preparation of traffic signal plans at Delany Road intersection with Continental Drive, and revisions and additions to the Plat of Highways prepared for the acquisition of necessary right-of-way.
Summary:
Original not to exceed contract amount for services described $644,693.72
Change Order 1 - 3 $64,114.94
Change Order No. 4 $ 174,564.83
Sum of all changes $ 238,679.77