Lake County, IL
File #: 09-2216    Version: 1 Name: Fairfield/ Gilmer/ Old McHenry Road Resurfacing Engineering Services: LCDOT Change Order No. 1
Type: committee action item Status: Joint Committee
File created: 11/20/2009 In control: Public Works and Transportation Committee
On agenda: Final action: 12/2/2009
Title: Joint committee action approving Change Order No. 1 consisting of an increase of $19,934.05 for additions to the Fairfield/ Gilmer/ Old McHenry Road Resurfacing’s Engineering Services, designated as Section No. 08-00999-01-RS.
Attachments: 1. 2216Fairfield CO1_20091120114126.pdf
Title
Joint committee action approving Change Order No. 1 consisting of an increase of $19,934.05 for additions to the Fairfield/ Gilmer/ Old McHenry Road Resurfacing's Engineering Services, designated as Section No. 08-00999-01-RS.
 
Staff Summary
·      Fairfield/ Gilmer/ Old McHenry Road Resurfacing Engineering Services:  LCDOT Change Order No. 1
·      Change Orders need to be approved by the standing committees for cumulative net increases over 10%.
·      The Fairfield/ Gilmer/ Old McHenry Road Resurfacing is under contract with McClure Engineering Associates Inc, in the amount of $99,553.80 originally assuming only local funding.
·      The consultant was directed to prepare the resurfacing plans in 3 formats during the time the LCDOT was attempting to get ARRA funding for all or a portion of these projects:
o      Fairfield, Gilmer and Old McHenry Roads for local letting
o      Gilmer and Old McHenry Roads for local letting
o      Fairfield Road for federal letting.
·      Lake County Council of Mayors "B List projects" were just recently federally funded due to low bids on the "A list projects".
·      Therefore the Fairfield Road portion will be federally let (Federal Funds @ $1,173,480 - 70%).
·      The Gilmer and Old McHenry portion will be locally funded and separately let.
·      Summary: original awarded contract - $99,553.80; Change Order No.1 - $19,934.05; sum of all changes - $19,934.05