Title
Joint committee action item approving Change Order No. 3 & Final consisting of an increase of $21,083.28 for additions to the 14th St. (Pulaski Dr.) Bridge Deck Resurfacing’s Construction Contract, designated as Section No. 08-00196-06-BR.
Staff Summary
• 14th St. (Pulaski Dr.) Bridge Deck Resurfacing: LCDOT Change Order No. 3 & Final
• Change Orders need to be approved by the standing committees for cumulative net increases over 10%.
• Pulaski Drive Bridge over US Rt. 41 Deck Repair and Resurfacing project is under an original awarded contract at bid unit prices totaling $306,779.42.
• This change order #3, in the amount of $21,083.28 is the final balancing change order to close out the contract.
• Change order #1 was mostly to add temporary pavement to use the shoulders for traffic instead of having to add a temporary traffic signal.
• Change order #2 was mostly for the additional patching found necessary in the first stage of construction and an estimate for stage #2.
• This change order #3 is for the final increased amount of patching and final measured quantities for balancing actual work completed on all unit price items (net $21,083.28).
• Summary: original awarded contract - $306,799.42; Change Order No. 3 - $21,083.28; sum of all changes - $114,266,20