Title
Joint resolution ratifying contracts with Wiss, Janney, Elstner Associates, Inc., Northbrook, Illinois, in the amount of $130,785.71, and Joseph J. Henderson & Son, Inc., Gurnee, Illinois, in the amount of $686,250 for an emergency procurement required for emergency repair work to one of the Lake County Division of Transportation's (LCDOT) facilities, and appropriating $818,000 of Motor Fuel Tax Funds.
Staff Summary
* LCDOT needed repair work completed on trusses in one of the facilities built in 1953, and the County Engineer declared an emergency for this repair work on February 5, 2024.
* In accordance with Article 6-103 of the Lake County Purchasing Ordinance, the County Engineer of Lake County certified an emergency procurement for contractual design and construction services.
* The firm selected to provide emergency contractual design services was Wiss, Janney, Elstner Associates, Inc., Northbrook, Illinois, in the amount of $130,785.71. The contractor selected to provide emergency contractual construction services was Joseph J. Henderson & Son, Inc., Gurnee, Illinois, in the amount of $686,250 based on a Facilities and Construction Services recommendation. The project was designated as Section 24-00214-27-MG.
* The repair work was completed on April 7, 2025.
* This resolution, per Article 6-103 of the Lake County Purchasing Ordinance, ratifies this emergency procurement contract and appropriates $818,000 of Motor Fuel Tax funds.
Body
RESOLUTION
WHEREAS, the Lake County Division of Transportation (LCDOT) owns and operates facilities within the Libertyville, Illinois, campus; and
WHEREAS, the trusses in the light duty shop at the LCDOT were at the end of their useful life and needed repair; and
WHEREAS, the LCDOT made improvements to its facilities, which included repairing trusses; and
WHEREAS, on February 5, 2024, in accordance with Article 6-103 of the Lake County Purchasing Ordinance, the County Engineer of Lake County declared that an emer...