Lake County, IL
File #: 10-0009    Version: 1 Name: Arlington Heights Rd. at Buffalo Creek (Northbound Bridge): Consultant Phase II Agreement
Type: resolution Status: Passed
File created: 12/23/2009 In control: Public Works and Transportation Committee
On agenda: Final action: 1/12/2010
Title: Joint resolution authorizing the execution of an agreement between Lake County and MACTEC Engineering and Consulting, Inc., Chicago, Illinois for Phase II professional engineering services for design of the replacement of precast concrete deck beams on the bridge carrying Arlington Heights Rd. over Buffalo Creek (northbound bridge). This resolution also appropriates $50,000 of County Bridge Tax funds for this improvement designated as Section 05-00193-04-BR.
Attachments: 1. 10 0009_20091228144229.pdf
Title
Joint resolution authorizing the execution of an agreement between Lake County and MACTEC Engineering and Consulting, Inc., Chicago, Illinois for Phase II professional engineering services for design of the replacement of precast concrete deck beams on the bridge carrying Arlington Heights Rd. over Buffalo Creek (northbound bridge). This resolution also appropriates $50,000 of County Bridge Tax funds for this improvement designated as Section 05-00193-04-BR.

Staff Summary
· Arlington Heights Rd. at Buffalo Creek (Northbound Bridge): Consultant Phase II Agreement and Appropriation
· All Phase II engineering for bridge deck beam replacement and design of traffic requirements to facilitate the proposed improvements.
· The selected and recommended consultant is MACTEC Engineering and Consulting, Inc., Chicago, Illinois at a maximum cost for services described of $40,924.
· This resolution authorizes the execution of a professional engineering services agreement with MACTEC Engineering and Consulting, Inc., Chicago, Illinois and appropriates $50,000 of County Bridge Tax funds for these services.

Body
R E S O L U T I O N

WHEREAS, Arlington Heights Rd. (County Highway 79) is a designated route on the county highway system; and

WHEREAS, the precast concrete deck beams of the bridge carrying northbound Arlington Heights Rd. over Buffalo Creek are at the end of their useful life; and

WHEREAS, the Illinois Department of Transportation (IDOT) has allocated Lake County federal Highway Bridge Replacement funds (HBR) for the proposed replacement of precast concrete deck beams of the bridge carrying northbound Arlington Heights Rd. over Buffalo Creek; and

WHEREAS, the Phase I preliminary engineering study for the proposed improvement has been completed, and Phase II design engineering needs to begin; and,

WHEREAS, it is advisable that a firm be employed to provide professional services for design of the replacement of the precast concrete deck beams on the ...

Click here for full text