Title
Joint committee action item approving Change Order Number Three consisting of an increase of $551,206 for additions to the Old McHenry Road / Quentin Road Phase I professional engineering services contract.
Staff Summary
• Change Orders need to be approved by the standing committees for cumulative net increases over 10 percent.
• The Old McHenry Road / Quentin Road project is under contract with TranSystems Corporation, Schaumburg, Illinois, in the amount of $6,177,075 as approved by the County Board on April 13, 2021, and designated as Section 19-00999-65-ES.
• The sum of all contract change orders to date is $1,145,937, which represents an 18.6% increase over the original awarded contract amount.
Body
JOINT COMMITTEE ACTION ITEM
Summary:
Original awarded contract: $6,177,075
Change Order Number Three: $ 551,206
Previously Approved Change Order Number Two: $ 594,731
Previously Approved Change Order Number One: Zero-Sum amount
Sum of all Change Orders: $ 1,145,937
Total revised contract amount (including all change orders): $7,323,012
Original contract appropriation amount: $7,415,000