Joint resolution appropriating $615,000 of Motor Fuel Tax funds for the resurfacing of Quentin Road, from Lake Cook Road to Long Grove Road, designated as Section 15-00051-10-RS.
Staff Summary
· Quentin Road Resurfacing, Lake Cook Road to Long Grove Road: Appropriation.
· Quentin Road, from Lake Cook Road to Long Grove Road, is in need of resurfacing.
· This resurfacing improvement has been identified within the County's pavement management system, and is included in the 2015 program.
· Before a project letting can be held, an appropriation of $615,000 of Motor Fuel Tax funds is necessary.
Body
R E S O L U T I O N
WHEREAS, Quentin Road, County Highway 5, is a designated route on the County highway system; and
WHEREAS, it would be beneficial to the safety and welfare of the motoring public if Quentin Road, from Lake Cook Road to Long Grove Road, is resurfaced; and
WHEREAS, plans, specifications and estimates of costs for this improvement have been completed, and this improvement is now ready to proceed to contract letting; and
WHEREAS, before a construction letting can be held, an appropriation of funds is needed.
NOW, THEREFORE BE IT RESOLVED by this Lake County Board, that there is hereby appropriated $615,000 of Motor Fuel Tax funds for the resurfacing of Quentin Road, from Lake Cook Road to Long Grove Road, and designated as Section 15-00051-10-RS.
BE IT FURTHER RESOLVED that this appropriation be processed by the County Engineer for final approval of the Illinois Department of Transportation in accordance with the "Agreement of Understanding" between the Illinois Department of Transportation and Lake County, dated January 18, 2013.
DATED at Waukegan, Illinois, on April 14, 2015.