File #: 08-0613    Version: 1 Name: Sidewalk Repairs and Replacement in Waukegan for Lake County
Type: resolution Status: Completed
File created: 8/28/2008 In control: Financial -FAS Department
On agenda: Final action:
Title: Resolution authorizing the Purchasing Agent to enter into a contract for Sidewalk Repairs and Replacement in Waukegan for Lake County with Boller Construction, Waukegan, IL, in the amount of $98,435.

Title

Resolution authorizing the Purchasing Agent to enter into a contract for Sidewalk Repairs and Replacement in Waukegan for Lake County with Boller Construction, Waukegan, IL, in the amount of $98,435.

 

Staff Summary

                     Lake County desires to enter into a contract with Boller Construction Co. Inc.

                     Lake County extended invitations for bid to seventeen (17) vendors.

                     Boller Construction Co., Inc., is the lowest responsive and responsible bidder.

                     Other bids were received ranging from $104.230 to $131,387.15.

                     This work will cost a total of $98,435.00.

 

Body

                     WHEREAS, in accordance with Section 4-102 of the Purchasing Ordinance of Lake County, Illinois, bids were called for by publication for Sidewalk Repairs and Replacement in Waukegan for Lake County; and

 

                     WHEREAS, subsequent to said publication, invitations for bids were extended to seventeen (17) vendors; and

 

                     WHEREAS, sealed bids were received from five (5) vendors and opened in the County Building, Waukegan, Illinois on Monday August 22, 2008, at 2:00 p.m.; and

 

WHEREAS, Boller Construction Co., Inc, of Waukegan, IL is the lowest responsive and responsible bidder for the Sidewalk Repairs and Replacement in the amount of $98,435.00, the other responsible bids received were from: Car-Min Construction Co., Inc, Waukegan, IL ,$104,230.00, M&A Cement Work, Inc., Bensenville, IL, $120,000.00Meridian Construction Co., Inc., Lake Bluff, IL, $127,206.00 and Dave’s Concrete, Round Lake, IL in the amount of $131.387.15.

 

NOW, THEREFORE, BE IT RESOLVED, by this County Board of Lake County, Illinois, that that the Purchasing Agent be authorized to enter into a contract for Sidewalk Repairs and Replacement in Waukegan for Lake County with Boller Construction, Waukegan, IL, in the amount of $ 98,435.00, charging the total cost to account #101-1103285-82020-000-000-000-11149 and requests its adoption.

 

DATED at Waukegan, Illinois, on this 9th day of September, A.D., 2008.