Title: Joint Committee action item approving IDOT Change Order No. 6 and final consisting of a reduction of $28,892.76 for final balancing revisions to the contract for the Rollins Road improvement from IL Rte. 83 to Drury Lane and designated as Section 99-00080-47-WR.
Attachments: 1. CO SIG PAGE ROLLINS_20090226085214.pdf, 2. C O 6 rollins _20090226084936.pdf
Title
Joint Committee action item approving IDOT Change Order No. 6 and final consisting of a reduction of $28,892.76 for final balancing revisions to the contract for the Rollins Road improvement from IL Rte. 83 to Drury Lane and designated as Section 99-00080-47-WR.
 
Staff Summary
·      Rollins Road from IL Rte. 83 to Drury Lane: IDOT Change Order No. 6 and Final
·      Change orders need to be approved by the standing committees for cumulative net increases over 10%.
·      The Rollins Road project is under contract at unit prices originally totaling $5,630,000.
·      This change order No. 6 is the final balancing change order for final costs based on actual work completed per final measurements and is a deduction of $28,892.76.
·      The major cost with earlier change orders was for the earth excavation for the entire roadway based on final cross sections.  
·      In summary:  original award was bid as unit prices and estimated quanities for $5,360,000; Change Order No. 1-5 was $1,188,939; Change Order No. 6 and final is -$28,892.76.  Summary of all changes is $1,160,046.24.