Title: Joint resolution authorizing a contract with Hoerr Construction, Inc., Goodfield, Illinois, in the amount of $71,225 to install cured-in-place pipe liners in culverts located on Miller Road and Deerfield Road, and appropriating $85,000 of County Bridge Tax funds.
Attachments: 1. 25-0423 Bid Tabulation - Culvert Lining 2025, 2. 25-0423 Vendor Disclosure, Hoerr, Culvert, 3. 25-0423 Location Map, Culvert Lining 2025
Title
Joint resolution authorizing a contract with Hoerr Construction, Inc., Goodfield, Illinois, in the amount of $71,225 to install cured-in-place pipe liners in culverts located on Miller Road and Deerfield Road, and appropriating $85,000 of County Bridge Tax funds.

Staff Summary
* Culverts #568 on Miller Road and #1344 on Deerfield Road are at the end of their service life and require rehabilitation with cured-in-place pipe liners.
* There was a public call for bids, and a total of four bids were received, ranging from $71,225 to $188,931, and the lowest responsible bidder is Hoerr Construction, Inc., Goodfield, Illinois, in the amount of $71,225.
* This project is included in the Transportation Improvement Program with construction to be completed in 2025 and designated as Section 24-00999-11-DR.

Body
RESOLUTION

WHEREAS, pursuant to authority granted by this County Board of Lake County, Illinois, the County Engineer heretofore called for sealed bids, by publication, for the installation of cured-in-place pipe liners in culverts on Miller Road and Deerfield Road, and designated as Section 24-00999-11-DR; and

WHEREAS, pursuant to said publication calling for said bid, sealed bids were received and opened on March 11, 2025, at 10:00 a.m. at the Lake County Division of Transportation in Libertyville, Illinois; a tabulation of said bids being as follows:

Hoerr Construction, Inc.
Goodfield, Illinois
$71,225

Insituform Technologies USA, LLC
Chesterfield, Missouri
$99,059

National Power Rodding Corp.
Chicago, Illinois
$107,806

Alliance Contractors, Inc.
Woodstock, Illinois
$188,931

WHEREAS, the Public Works and Transportation Committee, the County Engineer and the Purchasing Agent have examined each bid, and it appears that the lowest responsible bidder is Hoerr Construction, Inc., Goodfield, Illinois, their bid being $71,225, based on estimated quantities and unit prices; and

WHEREAS, an appropriation of funds is required.

NOW, THEREFORE, BE IT RESOLV...