Joint resolution appropriating a supplemental amount of $15,000 of Matching Tax funds for the design engineering of Quentin Road resurfacing, from Illinois Route 22 to Old McHenry Road, and designated as Section 10-00090-14-RS.
Staff Summary
· Quentin Road Resurfacing, Design Engineering Services; Change Order No. 1: Supplemental Appropriation.
· Additional design engineering services are required to design a steel retaining wall and resurface an additional 1000 feet.
· The original appropriation of $130,000 of Matching Tax funds needs to be supplemented by $15,000 to cover Change Order No. 1.
Body
R E S O L U T I O N
WHEREAS, this Lake County Board at its meeting of March 15, 2011, appropriated $130,000 of Matching Tax funds for the Phase II design engineering services for the Quentin Road proposed 2012 resurfacing from IL Route 22 to Old McHenry Road; and
WHEREAS, additional design engineering services are required to design a steel retaining wall and resurface an additional 1000 feet; and
WHEREAS, a supplemental appropriation of funds is necessary for the design engineering for the above described change of above-said improvement; and
WHEREAS, the Lake County Purchasing Ordinance requires the Public Works and Transportation Committee and the Finance and Administrative Committee to approve change orders with cumulative totals above 10% of the original contract.
NOW, THEREFORE BE IT RESOLVED that a supplemental appropriation of $15,000 of Matching Tax Funds is hereby authorized for the design engineering of the Quentin Road resurfacing from IL Route 22 to Old McHenry Road and designated as Section 10-00090-14-RS.
BE IT FURTHER RESOLVED, that this resolution being presented to the County Board for approval, the Public Works and Transportation Committee and the Finance and Administrative Committee hereby have approved change order #1.
DATED at Waukegan, Illinois...