Lake County, IL
File #: 13-0627    Version: 1 Name: 2012 Pavement Marker Replacement Program: Change Order No. 1
Type: committee action item Status: Passed
File created: 5/23/2013 In control: Public Works and Transportation Committee
On agenda: Final action: 5/29/2013
Title: Joint committee action item approving Change Order No. 1 for the 2012 Pavement Marker Replacement Program, consisting of an increase of $170,000 for additional services needed to remove and replace additional damaged raised reflective pavement markers throughout the County highway system, and designated as Section 12-00000-13-GM.
Attachments: 1. 13-0627 2012 Pavement Markers Change Order No. 1
Title
Joint committee action item approving Change Order No. 1 for the 2012 Pavement Marker Replacement Program, consisting of an increase of $170,000 for additional services needed to remove and replace additional damaged raised reflective pavement markers throughout the County highway system, and designated as Section 12-00000-13-GM.
 
Staff Summary
·      2012 Pavement Marker Replacement Program: Change Order No. 1.
·      Change Orders with a cumulative net increase over 10% must be approved by the standing committee and the Financial and Administrative Committee.
·      The 2012 Pavement Marker Replacement Program is under contract with Superior Road Striping, Inc., Melrose Park, Illinois, in the amount of $332,827.50.
·      Additional services, totaling $170,000, are needed to remove and replace additional damaged raised reflective pavement markers.
·      The County Board previously approved appropriations of $555,000 of Matching Tax funds for this work.