Lake County, IL
File #: 24-1570    Version: 1 Name: Approval of SIRF Eligibility authorization for Warren Township Highway Department’s N. Grandwood Drive Drainage Improvements Project
Type: commission action item Status: Passed
File created: 11/1/2024 In control: Lake County Stormwater Management Commission
On agenda: Final action: 11/7/2024
Title: Approval of the Stormwater Infrastructure Repair Fund (SIRF) Eligibility Authorization for Warren Township Highway Department's N. Grandwood Drive Drainage Improvements Project
Attachments: 1. Grandwood Drive Project Proposal, 2. Grandwood Drive SIRF Eligibility Authorization Form, 3. N Grandwood Map

Title

Approval of the Stormwater Infrastructure Repair Fund (SIRF) Eligibility Authorization for Warren Township Highway Department’s N. Grandwood Drive Drainage Improvements Project

Staff Summary

                     The proposed project would reduce roadway flooding at two township roads, a large undeveloped property, and 17 special hazard flood areas. The proposed project would also reduce flooding impacts on roadway access to over 100 residential properties.

                     The proposed project would replace, upsize, and construct new storm sewers along N. Grandwood Drive and adjacent properties.

                     The project may include enhancement to an existing swale on Lake County Public Works property as well as educational public information.

                     The estimated total project cost is $705,000. The project can be phased with an estimated Phase 1 Engineering and Design cost of approximately $126,000.

                     Approval of the Eligibility Authorization does not obligate funds. Staff will work with the project applicant to develop a Project Agreement and recommended funding.