File #: 25-1464    Version: 1 Name: Approval of an Intergovernmental Agreement between the SMC and the Village of Round Lake Beach for the Round Lake Drain Master Plan Phase 1 Project with a Project Expense Match (PEM) value of $48,356.17, subject to final legal review.
Type: commission action item Status: Passed
File created: 10/29/2025 In control: Lake County Stormwater Management Commission
On agenda: Final action: 11/6/2025
Title: Approval of an Intergovernmental Agreement between the SMC and the Village of Round Lake Beach for the Round Lake Drain Master Plan Phase 1 Project with a Project Expense Match (PEM) value of $48,356.17, subject to final legal review.
Attachments: 1. DCEO SMC Lake Beach IGA Round Lake Drain Ph 1, 2. Round Lake Drain Ph1 Location Map

Title

Approval of an Intergovernmental Agreement between the SMC and the Village of Round Lake Beach for the Round Lake Drain Master Plan Phase 1 Project with a Project Expense Match (PEM) value of $48,356.17, subject to final legal review.

 

Staff Summary

                     Funding for the intergovernmental agreement is included in Grant Agreement No. 24-413046 between Lake County and the Illinois Department of Commerce and Economic Opportunity (DCEO) that was executed December 15, 2024.

                     This project was authorized by SMC for inclusion in DCEO-STOCIP Regional Stormwater Infrastructure Project Round 2 on September 5, 2024.

                     The intergovernmental agreement will provide funding, on a reimbursement basis, in an amount not-to-exceed $1,825,450.00 for the Round Lake Drain Master Plan Phase 1 Project.  SMC will oversee bidding and project construction.

                     The Village of Round Lake Beach will pay a Project Expense Match to SMC of $48,356.17 for administrative and engineering expenses related to the project.