Title
Joint committee action item approving Change Order No. 4 & revised final consisting of a net decrease of $90,890.58 to the cumulative previous change orders to the Arlington Heights Road & Buffalo Grove Road Concrete Pavement Rehabilitation, designated as Section No. 08-00999-02-RP.
Staff Summary
· Arlington Heights Road & Buffalo Grove Road Concrete Pavement Rehabilitation: LCDOT Change Order No. 4 & Final
· Change Orders need to be approved by the standing committees for cumulative net increases over 10%.
· The Arlington Heights Road & Buffalo Grove Road Concrete Pavement Rehabilitation is under contract, at unit prices, with Vixen Construction, Inc. in the amount of $2,379,085.70.
· Previous Change Orders No. 1-3, as approved, were for additional work, and this Change Order No. 4 revised and final is the balancing change order for actual work completed at awarded unit prices.
· The balancing change order is a net decrease of $90,890.58 from the cumulative amount of Change Orders No. 1-3.
· Summary: Original awarded contract - $2,379,085.70; Change Order No. 4 & revised final: ($90,890.58); Sum of all changes - $663,667.68.