File #: 09-1733    Version: 1 Name: Fairfield Road at Gossell Road Intersection Improvement, Right-of-Way Acquisition: Appropriation with Condemnation Authority
Type: resolution Status: Passed
File created: 7/1/2009 In control: Public Works and Transportation Committee
On agenda: Final action: 7/14/2009
Title: Joint resolution appropriating $35,000 of Matching Tax funds for the acquisition of necessary right-of-way by agreement or condemnation, and other right-of-way costs associated with the proposed widening and resurfacing of the intersection of Fairfield Road and Gossell Road and designated as Section 01-00113-14-ES.
Related files: 10-0282

Title

Joint resolution appropriating $35,000 of Matching Tax funds for the acquisition of necessary right-of-way by agreement or condemnation, and other right-of-way costs associated with the proposed widening and resurfacing of the intersection of Fairfield Road and Gossell Road and designated as Section 01-00113-14-ES.

Staff Summary

                     Fairfield Road at Gossell Road Intersection Improvement, Right-of-Way Acquisition:  Appropriation with Condemnation Authority

                     Preliminary plans and specifications for this improvement have been prepared

                     Before right-of-way acquisitions can proceed an appropriation of $35,000 in Matching Tax funds and condemnation authority is necessary.

Body

 

WHEREAS, Fairfield Road (County Highway 49) is a designated route on the county highway system; and

 

WHEREAS, it would be beneficial to the safety and welfare of the motoring public if the intersection of Fairfield Road and Gossell Road could be improved by widening and reconstruction; and     

 

WHEREAS, Lake County by and through its Division of Transportation has caused to be prepared preliminary plans and right-of-way plats, said plats identifying right-of-way needs; and

 

WHEREAS, the right-of-way and associated costs are estimated to be $35,000.

 

NOW, THEREFORE BE IT RESOLVED by this County Board of Lake County, Illinois:

SECTION 1:  It is hereby determined that it is necessary and desirable that Lake County acquire title to and possession of all of the real property within the proposed new right-of-way lines of Fairfield Road at its intersection with Gossell Road together with construction and other easements, both temporary and permanent, for said highway, all as outlined in plats of highways made under direction of Martin G. Buehler, County Engineer of Lake County, Illinois, copies of which are filed in the office of the Lake County Engineer, which said real property and easements are necessary, required, and needed for the improvement of  said highway.

 

SECTION 2:  That the Lake County Division of Transportation, or its agents, on behalf of Lake County be, and they are hereby authorized, empowered and directed to negotiate with and purchase therefrom the owner or owners of all the real property determined to be necessary under this resolution and described in the plats of survey of said highway.

 

SECTION 3:  In the event that said Lake County Division of Transportation is unable to agree with the owner or owners of said real property upon the compensation to be paid therefore, then title to and possession of said real property described in Section 1 of this resolution shall be acquired by condemnation by Lake County.  The State’s Attorney of Lake County is hereby authorized, empowered and directed to institute proceedings in any court of competent jurisdiction to acquire title to and possession of said property for Lake County in accordance with the Eminent Domain Laws of the State of Illinois.

 

SECTION 4:  That there is hereby appropriated $35,000 of Matching Tax funds for the purchase of the real property determined to be necessary under this resolution and described in the plats of survey of said highway and designated as Section 01-00113-14-ES.

 

Dated at Waukegan, Illinois

this 14th day of July 2009