Title: Joint resolution authorizing an agreement with Christopher B. Burke Engineering, Ltd., Rosemont, Illinois, for Phase II design engineering services for traffic signal interconnect to Lake County PASSAGE, along various routes in Lake County, at a maximum cost of $653,648.93, appropriating $785,000 of ΒΌ% Sales Tax for Transportation and Public Safety funds, and designating as Sections 11-00088-19-TL, 11-00999-23-TL, 12-00103-17-TL, 12-00999-27-TL, 12-00999-25-TL, 12-00999-26-TL.
Attachments: 1. 12-0390 ITS Master Agreement Christopher Burke

Title

Joint resolution authorizing an agreement with Christopher B. Burke Engineering, Ltd., Rosemont, Illinois, for Phase II design engineering services for traffic signal interconnect to Lake County PASSAGE, along various routes in Lake County, at a maximum cost of $653,648.93, appropriating $785,000 of ¼% Sales Tax for Transportation and Public Safety funds, and designating as Sections 11-00088-19-TL, 11-00999-23-TL, 12-00103-17-TL, 12-00999-27-TL, 12-00999-25-TL, 12-00999-26-TL.

 

Staff Summary

                     Intelligent Transportation System (ITS) Lake County PASSAGE, Corridor Program: Christopher B. Burke Engineering, Ltd.: Consultant Agreement and Appropriation.

                     The Phase II design engineering services are to interconnect traffic signals along Aptakisic Road, Gilmer Road, Cedar Lake Road, Illinois Route 120, Illinois Route 83, and US Route 12 to Lake County PASSAGE.

                     Lake County has a satisfactory working relationship with Christopher B. Burke Engineering, Ltd., Rosemont, Illinois, under the Local Government Professional Services Selection Act.

                     This resolution authorizes the execution of a professional services agreement with Christopher B. Burke Engineering, Ltd., Rosemont, Illinois, for design engineering services at a maximum cost of $653,648.93, and appropriates $785,000 of ¼% Sales Tax for Transportation and Public Safety funds for that purpose.

                     Completing the design of these PASSAGE corridor signal interconnects, makes them eligible to compete for 100% federal Congestion Mitigation and Air Quality (CMAQ) program funding.

 

 

Body

R E S O L U T I O N

                     

WHEREAS, Lake County, by and through its PASSAGE Program, endeavors to interconnect traffic control signal systems situated throughout Lake County; and

 

WHEREAS, Lake County, by and through its Division of Transportation, plan to  interconnect traffic signals along Aptakisic Road, Gilmer Road, Cedar Lake Road, Illinois Route 120, Illinois Route 83, and US Route 12 to Lake County PASSAGE; and

 

WHEREAS, it is advisable that a professional engineering services firm be employed to provide Phase II design engineering services; and

 

WHEREAS, Lake County has selected a professional engineering services firm, Christopher B. Burke Engineering, Ltd., Rosemont, Illinois, in accordance with the Local Government Professional Services Selection Act, for said signal system enhancements including interconnection with PASSAGE.  

 

NOW, THEREFORE BE IT RESOLVED by this Lake County Board, that Christopher B. Burke Engineering, Ltd., Rosemont, Illinois, be employed to provide professional services to interconnect traffic signals along Aptakisic Road, Gilmer Road, Cedar Lake Road, Illinois Route 120, Illinois Route 83, and US Route 12 to Lake County PASSAGE, and that the County Board Chair, the County Clerk and the County Engineer of Lake County are authorized and they are directed to execute, on behalf of Lake County, a contract, a draft of which is attached hereto,  for the provision of said professional engineering services between Lake County and Christopher B. Burke Engineering, Ltd., Rosemont, Illinois.

 

BE IT FURTHER RESOLVED that the County Engineer shall transmit, in writing, the final agreement to be executed by the County Board Chair and the County Clerk.  

 

BE IT FURTHER RESOLVED that this agreement be administered in accordance with Chapter 605, Act 5, Section 5-205.2 of the Illinois Compiled Statutes without further Board action providing the final contract cost chargeable under the funds appropriated does not exceed the appropriation.

                     