Joint resolution ratifying a contract with RHMG Engineers, Inc., Mundelein, Illinois, in the amount not to exceed $58,412 to provide consulting services for the Bridlewood Reservoir Improvements Project.
Staff Summary
• On February 6, 2015, Public Works authorized a professional services contract in the amount of $44,516 with RHMG Engineers, Inc., Mundelein, Illinois, in accordance with the Local Government Professional Services Selection Act.
• The scope of work under this contract included design, bidding, and construction services for the reservoir improvements and a second set of bidding documents for the abandonment of well number seven for the Bridlewood Reservoir Improvements Project.
• A contract modification for additional services is required as a result of direction received during a variance hearing with the Lake County Zoning Board of Appeals for site revisions to CLCJAWA proposed improvements for the Lake Michigan Water Project, and the abandonment of well number six.
• This resolution ratifies the existing contract with RHMG Engineers, Inc., Mundelein, Illinois, in the amount of $44,516 and approves the contract modification of $13,896 to increase the existing contract to a not to exceed amount of $58,412.
Body
R E S O L U T I O N
WHEREAS, the County of Lake (County) owns, operates and maintains the Bridlewood Reservoir in Grandwood Park; and
WHEREAS, the Bridlewood Reservoir is in need of upgrades in preparation of Lake Michigan water delivery; and
WHEREAS, due to the specialized nature of this project, the County requires design services from an engineering firm qualified in this type of engineering; and
WHEREAS, as part of the design for the project, Public Works authorized a professional services contract in the amount of $44,516 with RHMG Engineers, Inc., Mundelein, Illinois in accordance with Local Government Professional Services Selection Act (50 ILCS 510/1 et. seq.); and
WHEREAS, the scope of work under this contract included design, bidding, and construction services for the reservoir improvements and a second set of bidding documents for the abandonment of well number 7 for the Bridlewood Reservoir Improvements Project; and
WHEREAS, a contract modification for additional services is required as a result of direction received during a variance hearing with the Lake County Zoning Board of Appeals for site revisions to CLCJAWA proposed site improvements for the Lake Michigan Water Project, and the abandonment of well number 6; and
WHEREAS, this resolution ratifies the existing contract with RHMG Engineers, Inc., Mundelein, Illinois in the amount of $44,516 and approves the contract modification to increase the existing contract to a not to exceed amount of $58,412; and
NOW, THEREFORE, BE IT RESOLVED, by this County Board of Lake County, Illinois, that the County Board ratifies a contract with RHMG Engineers, Inc. in a not to exceed amount of $58,412 to provide consulting services for the Bridlewood Reservoir Improvements Project, charged to account number 610-4853506-71170-000-000-000-48310 and 610-4843598-71170-000-000-000-48310.