Title: Joint committee action approving Change Order Number One for the SEC Des Plaines River Siphon and Chamber Lining with Visu-Sewer of Illinois, LLC resulting in a net cost reduction of $49,488 from $252,500 to $203,012.
Attachments: 1. 23-0159 SEC Siphon Lining Neg Final CO#1 Committee Action Item 2020.091 TFM, 2. Visu Sewer Vendor Disclosure

Title

Joint committee action approving Change Order Number One for the SEC Des Plaines River Siphon and Chamber Lining with Visu-Sewer of Illinois, LLC resulting in a net cost reduction of $49,488 from $252,500 to $203,012.

 

Staff Summary

                     On May 13, 2021, a contract was issued to Visu-Sewer of Illinois, LLC to install a liner in the 230-foot-long parallel 24-inch diameter and 36-inch diameter concrete pipes under the Des Plaines River and spray line the inlet and outlet chambers.

                     The construction was completed with one mobilization instead of two resulting in a savings for matting and restoration.

                     Change Order One accounts for the reduction in work at the contracted unit prices, resulting in a decreased cost of $49,488 for the project.

                     In accordance with Section 33.082 of the Lake County Purchasing Ordinance, when the total of change orders, contract modifications, or price adjustments on any contract approved by resolution by the County Board exceeds 10 percent of the original contract amount, approval of the standing committee in charge of the contracting department or agency and the Financial and Administrative Committee is required.

                     This joint committee action authorizes and directs the Purchasing Agent to execute a contract change order with Visu-Sewer of Illinois, LLC, reducing the original contract value by $49,488 from $252,500 to $203,012.

 

Body

JOINT COMMITTEE ACTION

 

 

TO: Chair, Public Works & Transportation Committee

       Chair, Financial & Administrative Committee

      

FROM: RuthAnne K. Hall, Purchasing Agent

 

DATE: February 1, 2023

 

RE: Joint committee action approving Change Order One to the agreement with Visu-Sewer of Illinois, LLC

 

1.                     On May 13, 2021, a contract was issued to Visu-Sewer of Illinois, LLC to install a liner in the 230-foot-long parallel 24-inch diameter and 36-inch diameter concrete pipes under the Des Plaines River and spray line the inlet and outlet chambers.

 

2.                     The construction was completed with one mobilization resulting in a savings for matting and restoration.

 

3.                     Change Order One accounts for the reduction in work at the contracted unit prices, resulting in a decreased cost of $49,488 for the project.

 

4.                     In accordance with Section 33.082 of the Lake County Purchasing Ordinance, when the total of change orders, contract modifications, or price adjustments on any contract approved by resolution by the County Board exceeds 10 percent of the original contract amount, approval of the standing committee in charge of the contracting department or agency and the Financial and Administrative Committee is required.

 

5.                     This joint committee action authorizes and directs the Purchasing Agent to execute a contract change order with Visu-Sewer of Illinois, LLC, reducing the original contract value by $49,488 from $252,500 to $203,012.