Legislation Details

File #: 20-0384    Version: 1 Name: Rollins Road Drainage: Change Order Number Five
Type: committee action item Status: Passed
File created: 2/21/2020 In control: Public Works, Planning & Transportation Committee
On agenda: Final action: 3/5/2020
Title: Joint committee action item approving Change Order Number Five consisting of an increase of $6,412.44 for additions to the Rollins Road drainage construction contract.
Attachments: 1. 20-0384 Copenhaver Vendor Disclosure

Title

Joint committee action item approving Change Order Number Five consisting of an increase of $6,412.44 for additions to the Rollins Road drainage construction contract.

 

Staff Summary

•                     Change Orders need to be approved by the standing committees for cumulative net increases over 10 percent.

•                     Rollins Road drainage project is under contract with Copenhaver Construction Inc., Gilberts, Illinois, in the amount of $297,159.36 as approved by the County Board on August 8, 2017, and designated as Section 15-00080-60-DR. 

•                     The contract included storm and sanitary removal and replacement; sodding (complete); erosion control; storm and sanitary structure removal, adjustment, and installation; trench backfill; hot-mix asphalt surface course; class D patches; and other related items.

•                     Change Order Number Five consists of balancing earthwork and other minor items to final measured quantity.

•                     Change Order Number Four was for additional work to fit to field conditions including a driveway replacement not originally anticipated, landscaping and sanitary manhole adjustment.

•                     Change Order Number Three was for balancing quantities to field measurements and adding items for a sanitary manhole rebuild that was not anticipated, a boulder obstruction and repairing unmarked sanitary facilities that belong to the Lakes Regional Sanitary District.

•                     Change Order Number Two was for underground traffic interconnect conduit relocation that was in conflict and some other minor field adjustments.

•                     Change Order Number One was for adjustments to interconnect wire, additional tree removal that was not anticipated and other minor field adjustments.

•                     Lakes Regional Sanitary District has already reimbursed per agreement for their facilities $51,612.21.

 

Body

COMMITTEE ACTION ITEM

 

Summary:

 

Original awarded contract:                     $297,159.36

 

Change Order Number One:                              -$1,434

Change Order Number Two:                        $10,100.90

Change Order Number Three:                          $5,718.29

Change Order Number Four:                        $15,128.09

Change Order Number Five:                          $6,412.44

Sum of all Change Orders:                        $35,925.72

 

Total revised contract amount (including all change orders): $333,085.08

 

Original contract appropriation amount:  $440,000